Wednesday 10 March 2010

Update on Building Progress

The contract commenced November 2009
• Development progressing well, despite recent poor weather conditions
  • Opening due in October 2010
Current Work:
• Phase 1 – wet side development (the pool and new changing rooms)
• Phase 2 – youth facilities
Management and Operations
Additional funds secured, which include:
• Southwark Council Leisure Investment Fund
• Cleaner Greener Safer (£52K)
• London Marathon Charitable Trust (£100K )

New funds will contribute to phase 3 - improving the outside area (Artichoke Place), and upgrade of Dry side facilities